Home Products Solutions Process Blog About Contact
Home · Blog · Current Transformers
Technical Guides

Current Transformer Testing: Ratio, Polarity and Burden Checks

ET
ET Engineering Team October 29, 2026 10 min read
Technician checking the secondary leads of a split-core current transformer clamped on a copper busbar with a portable test instrument on a workshop bench

A current transformer is tested before it is connected to a meter for four reasons: to confirm the ratio matches the nameplate, to confirm the polarity of the secondary, to confirm the secondary burden is within what the core can actually drive, and to confirm that the insulation between primary, secondary and earth is intact. On a low-voltage metering CT those four checks take well under fifteen minutes per unit, and each one catches a fault that would otherwise appear as a wrong bill instead of a dead circuit.

That last point is the reason testing matters more on a CT than on a breaker. A breaker that fails is obvious. A current transformer that fails is usually silent, and the installation keeps working perfectly while the numbers it produces are wrong.

Why a CT fails quietly

A current transformer has no moving parts, no trip mechanism and no indication of its own. It simply reports a scaled copy of the primary current into the meter. If that copy is scaled by the wrong factor, inverted, or clipped, nothing trips and nobody is alerted.

Step 1: nameplate and physical check

Before any instrument is connected, read the rating plate and compare it with the meter's programmed CT ratio and with the purchase order. The classification, the rated primary and secondary current, the rated burden and the rated voltage all appear there. Three things are worth checking with your hands as well as your eyes:

Step 2: insulation resistance

With the CT completely isolated, the meter disconnected and the secondary temporarily shorted or connected to the tester as your procedure requires, measure insulation resistance primary-to-secondary and secondary-to-earth. The purpose is not to grade the transformer; it is to prove there is no path that should not exist before the circuit is made live.

One safety rule sits above every measurement in this article: never open-circuit the secondary of a current transformer while primary current is flowing. An open secondary removes the opposing flux, the core drives into saturation, and a very high voltage appears across S1 and S2. Always short the secondary through a test block or a dedicated shorting link before breaking the loop.

Step 3: ratio test

The ratio is the primary current divided by the secondary current, so a 200/5 unit has a nominal ratio of 40:1. Two methods are used in the field, and both are legitimate:

MethodHow it worksWhere it is the better choice
Primary injectionA high-current test set injects a known current through the primary window while the secondary current is measured directly.Commissioning a panel, where a primary injection set is already on site and the whole metering loop can be proved at once.
Secondary voltage methodA low AC voltage is applied to the secondary and the induced primary voltage is measured. The voltage ratio equals the turns ratio, which equals the current ratio.Bench testing individual units, or anywhere a primary injection set cannot be brought.

Record the measured ratio, not just a pass or fail. A unit that measures 39:1 against a nominal 40:1 is behaving normally; one that measures 25:1 has a closure or winding problem and will under-read by a third for the rest of its service life.

Step 4: polarity test

Polarity is the relationship between P1 and S1. The convention is that current entering the primary at P1 leaves the secondary at S1. Get it backwards and the meter sees the opposite sign.

The classic field method is the DC flick test. A battery is briefly applied across the primary and an analogue or moving-coil instrument watches the secondary. When the battery is connected, a correctly polarised CT produces a deflection in the marked direction; when it is removed, the deflection reverses. A digital meter with a polarity or ratio function does the same job with less interpretation. If a known-good transformer of the same type is available, comparing the two is the fastest confirmation of all.

Mark the result on the unit. Polarity is easy to check once and almost impossible to remember six months later when a meter is replaced.

Step 5: burden test

Burden is the load the secondary circuit presents to the CT, expressed in volt-amperes at rated secondary current. It is made up of the meter's current circuit, the terminal blocks, and above all the length and cross-section of the secondary cable. A CT rated for a stated burden will hold its accuracy up to that figure and no further.

What adds burdenWhy it matters
Long secondary runsResistance rises with length, and burden rises with the square of secondary current, so a long 2.5 mm² run is a common cause of saturation.
Undersized secondary cableThe cheapest way to overshoot a CT's rated burden without noticing.
Extra devices in the loopEach additional meter, relay or terminal pair adds impedance in series.
Poor terminationsA high-resistance joint behaves like extra cable and heats under load.

Compare the calculated loop burden with the CT's rated burden. If the loop is close to the limit, move up to the next CT size or increase the secondary cross-section. Both are cheaper than a meter that under-reads on peak.

Metering cores and protection cores need different emphasis

The same four tests apply to both, but what you are proving is not the same thing.

Core typeWhat the test must establishFailure that matters most
Metering core (class 0.5, class 1.0)Accuracy at normal load, correct ratio, correct polarityA small ratio error or a reversed secondary, because both distort billing continuously
Protection core (5P, 10P)Behaviour at high fault current, composite error at the accuracy limit factorSaturation before the fault level, which delays or prevents a trip

Symptoms and their usual cause

What the site reportsCheck first
Consumption reads consistently low against a check meterProgrammed CT ratio and actual ratio; then burden and secondary cable size
Meter registers export on a load that only importsSecondary polarity at S1/S2
Readings are acceptable at light load and fall away at peakSaturation: burden, cable length and core closure on split-core units
Readings jump or drift between visitsLoose secondary terminal or a latch that is not fully closed

Split-core units: the closing faces are the test

Split-core current transformers are installed around a cable or bar without disconnecting it, which is exactly why they are popular for retrofits and for sub-metering in occupied buildings. The trade-off is that the magnetic circuit is only as good as the joint between the two halves. Clean the faces, close the latch fully, and confirm the measured ratio after installation rather than assuming it. YOMIN builds split-core units such as the 720V AC 2000/5A Class 0.5 split-core CT and the DP-816 1000/5A Class 0.5 split-core unit, both intended for metering duty.

Low-voltage CTs for metering panels

For panel builders specifying by ratio and accuracy class rather than by core type, the catalogue covers the usual metering range:

Model referenceRatio and classTypical use
Split-core CT, 2000/5 A2000/5 A, class 0.5, 720 V AC, single phaseRetrofit sub-metering on large feeders without disconnection
DP-816, 1000/5 A1000/5 A, class 0.5, 720 V AC, split coreDistribution board metering where cables cannot be broken
MR-85 series, 5000/5 A5000/5 A, class 0.5 / 1.0, single phaseMain incoming metering on high-current low-voltage boards
MSQ-0.66-30I, 150/5 A150/5 A, class 0.5, low voltage, toroidalFeeder and machine-level metering in a compact window

Two ratios worth remembering when ordering: the secondary is normally 5 A, and the ratio written on the order should always be the primary/secondary pair, never the primary alone. See our notes on how CT ratios are expressed and on what the accuracy class actually promises before finalising a schedule.

Commissioning checklist

Frequently asked questions

Can I test a current transformer without a primary injection set?

Yes. The secondary voltage method needs only a low AC source and a voltmeter, and it proves the turns ratio directly. What it does not prove is the complete loop including the primary conductor, so a primary injection test is still preferable at commissioning when the equipment is available.

Why does my meter read low only at peak load?

That pattern points to saturation rather than a ratio error. The secondary burden is too high for the core, usually because of long or undersized secondary cable, and the CT stops tracking current once the load approaches its accuracy limit.

What happens if a CT secondary is left open?

With primary current flowing, an open secondary allows the core flux to rise unchecked and a very high voltage develops across S1 and S2. It is a shock hazard and it can destroy the winding. Always short the secondary before opening the circuit.

Do split-core CTs need re-testing after installation?

They should be. The ratio depends on the two halves closing completely, and that is a mechanical condition affected by paint, grit and latch tension. A ratio check after closing takes a minute and catches the most common split-core fault.

Testing CTs on a metering project?

Send the ratio, accuracy class and secondary cable length for each point, and we will confirm the CT and the burden before the panel is wired.

Request a quote

Browse current transformers →

Prefer to send the schedule on WhatsApp? +86 190 1654 3301