Energy Meter Wiring Diagram: Single-Phase, Three-Phase and CT-Operated Meters

ET
ET Engineering Team October 29, 2026 9 min read
Electrician wiring the terminal block of a DIN-rail energy meter inside an open distribution enclosure with a fine screwdriver

An energy meter wiring diagram is read from the terminal block, not from the display. A single-phase meter has four power terminals: line in, line out, neutral in and neutral out. A three-phase four-wire meter has seven: three line in/out pairs plus neutral in and out. A CT-operated meter replaces the heavy current terminals with small secondary terminals, two per current transformer. Everything else on the meter, meaning RS485, pulse output and tariff control, is low-voltage signalling and belongs to a separate terminal group.

Getting the power terminals right decides whether the meter works; getting the small terminals right decides whether it keeps working. Most meters that come back as failed in the first year were not faulty in the factory, they were miswired on site.

Before any wire goes in

Three checks save most of the callbacks.

Single-phase two-wire: four terminals

The most common DIN-rail meter in the world, and the one most often wired backwards.

TerminalConnectionWhat goes wrong
L in (often 1)Incoming live from the supply sideSwapped with L out, so the meter still counts but the installation's polarity downstream is reversed
L out (often 2)Live to the loadLoad taken from the incoming side, bypassing the meter entirely
N in (often 3)Incoming neutralNeutral borrowed from another circuit, which puts unmeasured current through the meter's reference
N out (often 4)Neutral to the loadNeutral and earth confused, which is both a metering error and a safety fault

The single-phase electronic meter in the YOMIN range, such as the mini DIN-rail single-phase kWh meter, follows this four-terminal arrangement in a two-module body. Where RS485 is included, as on the 80 A RS485 DIN-rail meter, the communication terminals sit apart from the power terminals and are clearly marked A and B.

Three-phase four-wire: seven terminals

Three line conductors and one neutral, each measured on its own element. The neutral is not optional on a four-wire meter: without it the voltage reference for each element is wrong and the readings are meaningless rather than merely inaccurate.

GroupTerminalsNotes
Line, phase 1L1 in, L1 outPhase sequence should follow the printed diagram; the meter will run with any sequence but the per-phase registers will not correspond to your labelling.
Line, phase 2L2 in, L2 outSame element arrangement as phase 1
Line, phase 3L3 in, L3 outSame element arrangement as phase 1
NeutralN in, N outMust be the same neutral that serves the load, not a borrowed one

A current range such as 5–80 A on the 380 V 50 Hz three-phase four-wire DIN-rail meter describes a direct-connected device: the load current passes through the meter's own terminals. Above that current, the meter must be CT-operated instead. Our guide to three-phase meters covers the 3-wire and 4-wire distinction and the direct versus CT decision in more detail.

CT-operated meters: small terminals, large consequences

On a CT-operated meter the heavy conductors pass through the current transformers and never touch the meter. The meter receives the secondary of each CT, normally 5 A, on a pair of small terminals marked S1 and S2.

The three-phase DIN-rail meter with CT input and M-Bus is built for this arrangement, and our notes on CT-operated metering explain how the ratio interacts with the register.

RS485 and pulse outputs

These terminals carry no load current, but they are the ones that fail quietly when they are wired carelessly.

SignalTerminalsPractice
RS485A and B, sometimes with a commonShielded twisted pair, daisy-chained rather than star-wired, shield earthed at one end only, A to A and B to B throughout the bus
Pulse outputPulse and commonTwo-core screened cable kept away from power conductors; the pulse constant printed on the meter defines what each pulse is worth
Tariff controlSwitched inputDry contact from the tariff clock or controller, never a stolen live

Keep signal and power conductors in separate ducts wherever the route allows it. Most intermittent communication faults on a metering installation are induced noise from a signal cable run alongside a feeder, not a failed meter. The Modbus and RS485 buyer's guide covers addressing and termination.

Meter family at a glance

FamilyPower terminalsSignal terminalsTypical model
Single-phase two-wire, direct4Pulse, optional RS485Mini DIN-rail single-phase kWh meter
Single-phase, direct, communicating4RS485, pulse80 A RS485 DIN-rail meter
Three-phase four-wire, direct7RS485, pulse380 V 50 Hz three-phase four-wire meter
Three-phase, CT-operated3 pairs S1/S2M-Bus, infraredThree-phase CT-input meter with M-Bus

Mistakes that account for most failures

MistakeResult
Load tapped from the incoming side of the meterThe meter is bypassed and registers nothing for that load, while still appearing to work
Neutral taken from a different circuitPart of the current returns outside the meter; readings drift and become irreconcilable
Two phases transposed on a three-phase meterTotal may look acceptable while per-phase data is wrong, so fault-finding on the site is misled
CT secondary reversedOne phase registers negative; the total understates consumption
CT ratio not programmedEvery reading scaled by the wrong factor, with no visible symptom
RS485 star-wired instead of daisy-chainedReflections and intermittent dropouts on the bus
Signal cable run in the power ductNoise-induced errors that appear and disappear with load

Commissioning checklist

Frequently asked questions

Can a single-phase meter be connected with line and neutral reversed?

Many electronic meters will still count, because they measure the potential difference across the element rather than assuming which side is live. That does not make it correct: the downstream polarity of the installation becomes reversed and the neutral becomes switched. Wire it to the diagram.

Why does my three-phase meter show one phase negative?

Almost always a reversed CT secondary on that phase, or a CT installed with P1 facing the load instead of the supply. Check polarity at S1/S2 before suspecting the meter.

Do I need to program the CT ratio, or does the meter detect it?

You must program it. The meter sees only secondary current and has no way to know what primary current that represents. An unprogrammed ratio is the most common cause of a meter that reads a plausible but wrong figure.

How far can an RS485 run be on a metering installation?

It depends on baud rate, cable capacitance and how many devices share the bus, which is why the practical answer comes from the meter's datasheet rather than a rule of thumb. What matters at any length is daisy-chain topology, consistent A/B polarity and a shield earthed at one end only.

Wiring meters on a project?

Send the meter type, supply arrangement and CT ratio for each point, and we will confirm the terminal configuration before the panel is built.

Request a quote

Browse energy meters →

Prefer to send the metering schedule on WhatsApp? +86 190 1654 3301